Demo

Search

Make your choice from the menu on the left side. Selected risks are shown below. If you want to limit the number of risks, select properties of the risks thats are important to you in the left menu.


      
= LOW risk level
      
= MED risk level
      
= HIGH risk level
User:
TestUsers
Client:
Costa Renewables
@Risk:
0.9 M€
Mitigated:
0.0 M€
Remaining:
0.9 M€
1 - 1 of 1 risks, sort by
During construction it is necessary to evacuate the tower . The protection for the crane and crane vessel needs to be verified and announced to Contractor crew.
Investigation of the earthing between the crane and the barge? Determine appropriate protection procedures during a lightning storm.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
1 - 1 of 1 risks, sort by