Costa Renewables
@Risk:
86.4 M€
Mitigated:
0.0 M€
Remaining:
86.4 M€
1 - 3 of 3 risks, sort by
Adverse effects on fish
Temporary hearing loss and disorientation for fish, as well as tissue damage and even death for fish arising during construction activities, specifically from the installation of the turbine bases by piling.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
41,250 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Displacement
Possible impacts forced movement out of foraging or reproductive areas
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
41,250 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Adverse effects on marine mamals
Possible impacts arising from the proposed development include damage to hearing either permanently or temporarily from noise arising during construction activities, specifically from the installation of the turbine bases by piling. There is potential for noise arising from the construction, operation and decommissioning of the proposed development to cause either behavioural responses to, or displacement of marine mammals in the area of affect. There are also possible physical impacts to marine mammals from either collisions with vessels or impacts with vessel’s thrusters.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
3,938 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified