Make your choice from the menu on the left side. Selected risks are shown below. If you want to limit the number of risks, select properties of the risks thats are important to you in the left menu.


      
= LOW risk level
      
= MED risk level
      
= HIGH risk level
User:
TestUsers
Client:
Costa Renewables
@Risk:
0.2 M€
Mitigated:
0.1 M€
Remaining:
0.1 M€
1 - 7 of 7 risks, sort by
Standby required to prevent access to the area and act as a rescue boat during the construction phase. During maintenance operations the transfer boat will act as standby boat if permit does not require that.
Standby/transfer boats should be hired from and operated by a sub contractor of contractor.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
2 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Fire, electrical fault
smoke inhalation, injury due to no early warning
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
2 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Some birds will be killed by the turbines. Most birds will deviate their flight path around the wind farm.
Is there a requirement to monitor bird kills (Wtbird system)?. Will there be observers during construction?.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
17 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential for operators to get stranded in tower overnight
Survival facilities provided for how many days?
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
2 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
May be difficult to transfer tools to top of tower
Crane provided on platform designed for tools
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
17 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Sandbanks are continuously moving which might expose cables and cause excessive scour. Scour around jack-up legs could cause the vessel to tip over.
Monitoring and periodic inspection. Scour protection is considered conservative. Baseline survey to be completed of seabed morphology. A second survey should be commissioned for after construction (five years).Monitoring on vessel legs during jacking.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
13 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Vessel crew not trained and educated according to the requirements for the vessel / barge or harvesting the seaweeds
Inadequate response or lack of preventive maintanance of the vessel / barge.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
17 k€
Due in:
2 years ago
Owned by:
Rob Tegel
Status:
Mitigated
Priority:
High
Last updated:
2 years ago