Costa Renewables
@Risk:
7.6 M€
Mitigated:
0.0 M€
Remaining:
7.6 M€
1 - 10 of 17 risks, sort by
Lifting of main components on outside of tower.
Load calculations for workplatform and other components / equipment influenced by weight. These are critical operations
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Fire in turbine
High temperature and gas sensors with shutdown function
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Unexperienced people hired. This is a new type of project and experienced people for marine operations are recognised as crucial to the projects success.
Train and education according to STCW 95 standards and wind park & contractor training matrix to be reflecting that.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential for critical failures if key equipment fails during heavy lifts etc.
These are critical operations
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Concurrent operations risk with commissioning and start-up at the same time
Adequate interface with grid owner and procedure for energising.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Electrocution
Step potentials - LV/HV
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Bad weather/ high waves / Injury
Falling, Crushing, stranding, drowning
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential risk of incidents if inadequate handover
Will be easier if all crew changes are conducted in the harbour but possible to change crew on location
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential H2S formation in water in the monopile
Reduced oxygen in the air, will be considered as a confined space.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
53 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Diving operations which are regarded as very hazardous. (Divers required for inspection of e.g. marine growth, cable entrance, scour during operation & maintenance)
Diving operations and and harvesting of seawed operations should be assessed.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
1 - 10 of 17 risks, sort by