Costa Renewables
@Risk:
3.0 M€
Mitigated:
0.1 M€
Remaining:
2.9 M€
1 - 10 of 14 risks, sort by
Lifting of main components on outside of tower.
Load calculations for workplatform and other components / equipment influenced by weight. These are critical operations
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Some birds will be killed by the turbines. Most birds will deviate their flight path around the wind farm.
Is there a requirement to monitor bird kills (Wtbird system)?. Will there be observers during construction?.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
17 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential for critical failures if key equipment fails during heavy lifts etc.
These are critical operations
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Concurrent operations risk with commissioning and start-up at the same time
Adequate interface with grid owner and procedure for energising.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Electrocution
Step potentials - LV/HV
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Bad weather/ high waves / Injury
Falling, Crushing, stranding, drowning
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Unexperienced people hired. This is a new type of project and experienced people for marine operations are recognised as crucial to the projects success.
Train and education according to STCW 95 standards and wind park & contractor training matrix to be reflecting that.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential for operators to get stranded in tower overnight
Survival facilities provided for how many days?
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
2 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Some sub-contractors may not have much offshore experience
HSE capabilities are assessed as part of tendering process including training, competence etc. in all phases of project
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
May be difficult to transfer tools to top of tower
Crane provided on platform designed for tools
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
17 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
1 - 10 of 14 risks, sort by