Costa Renewables
@Risk:
184.6 M€
Mitigated:
0.1 M€
Remaining:
184.5 M€
21 - 30 of 32 risks, sort by
Diving operations which are regarded as very hazardous. (Divers required for inspection of e.g. marine growth, cable entrance, scour during operation & maintenance)
Diving operations and and harvesting of seawed operations should be assessed.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Financial impact:
53 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
access and egress from quayside to vessels and from vessel to vessel and vessel to WTG
Person could fall in sea water, drown get under cooled, get caught between two objects, trip, slip hazards
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential damage to cables
Cables buried to 1,5 m. The route will be included on charts as a no-anchoring zone and is clear from local oil/gas pipelines and telecommunications cables.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Accidents during service period due to large number of vessel and ship movements
Risk gives: HSE issues; and/or damage of equipment; and/or delay in work due to e.g. authorities investigation. The Work Vessel coordinator should ensure proper communication between the vessels, and will know where the vessels are.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential risk of incidents if inadequate handover
Will be easier if all crew changes are conducted in the harbour but possible to change crew on location
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Unexperienced people hired. This is a new type of project and experienced people for marine operations are recognised as crucial to the projects success.
Train and education according to STCW 95 standards and wind park & contractor training matrix to be reflecting that.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
289 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential for operators to get stranded in tower overnight
Survival facilities provided for how many days?
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
2 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Potential H2S formation in water in the monopile
Reduced oxygen in the air, will be considered as a confined space.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
53 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
During construction it is necessary to evacuate the tower . The protection for the crane and crane vessel needs to be verified and announced to Contractor crew.
Investigation of the earthing between the crane and the barge? Determine appropriate protection procedures during a lightning storm.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
919 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
21 - 30 of 32 risks, sort by