Costa Renewables
@Risk:
184.6 M€
Mitigated:
0.1 M€
Remaining:
184.5 M€
31 - 32 of 32 risks, sort by
Sandbanks are continuously moving which might expose cables and cause excessive scour. Scour around jack-up legs could cause the vessel to tip over.
Monitoring and periodic inspection. Scour protection is considered conservative. Baseline survey to be completed of seabed morphology. A second survey should be commissioned for after construction (five years).Monitoring on vessel legs during jacking.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
13 k€
Due in:
Not specified
Owned by:
No owner assigned
Status:
Not mitigated
Priority:
No priority given
Last updated:
Not specified
Vessel crew not trained and educated according to the requirements for the vessel / barge or harvesting the seaweeds
Inadequate response or lack of preventive maintanance of the vessel / barge.
Likelihood to occur:
       
 
Consequences:
       
 
Financial impact:
17 k€
Due in:
2 years ago
Owned by:
Rob Tegel
Status:
Mitigated
Priority:
High
Last updated:
2 years ago